An update on Roxwell!
11/03/2025
Our Roxwell Road project continues to storm ahead. In the coming weeks we will be handing over the first flats in Block A. The electrical heads are now installed and live to blocks A and B and internal painting is taking place in the flats.
The brickwork to Blocks A, B and C is now complete and Blocks D and E are not far behind.
In Blocks A and B, the scaffolding at the back of the building has come down and that on the front elevation will be dismantled over the next month. Internal works are going at pace and include painting, mechanical and electrical works, flooring, tiling, carpentry and second fix items.
In Block C we are continuing drylining, M&E First Fix and screeding soon we will be dismantling the scaffolding.
The full development will be completed in March 2026. This is a fantastic project and Jerram Falkus are delighted to continue to be a part of the development of this corner of Barking.