Projects

Latymer Upper School Sports Facility

Works comprised the construction of a new three-storey sports centre extension to the existing facility which provided a new 25 metre 6 lane swimming pool with automated moving floor, dance and fitness studios, wet and dry changing facilities, WC’s, stores and offices.

 

Piled foundations and waterproof reinforced concrete basement and swimming pool, reinforced concrete frame with Metsec inner walling system and externally clad with Fibre-C panels, Reglit glazing and insulated Sto render.

 

Extensive mechanical and electrical services included pool filtration and heating plant, roof mounted air handling, and cooling to the dance and fitness studios.The existing adjacent Sport Hall was refurbished including new external insulated Fibre-C wall cladding, roof cladding, new sports floor, internal fitting out and new services including heating, ventilation and lighting.

Other Projects

Park Primary School

The school expansion was carried out in three phases. The first phase provides four new classrooms and a new main entrance. Phase 2 remodelled existing classrooms into WC accommodation and phase 3 adds a new multi-purpose hall, raised on angled stilts, creating a mini MUGA court underneath and a roof terrace focused around a new […]

Read More

St Benedict’s School, New Ark

St Benedict’s is a leading independent catholic co-educational school providing education from nursery through to sixth form. We were appointed after the success of the Sixth Form and Art Design & Technology Building. This project, the New Ark, will re-provide classrooms for the Junior School and bring the Nursery on to the school site in […]

Read More

New Grandview, Oakwood Adult Autism Unit

The New Grandview Oakwood Adult Autism Unit provides long term specialist residential accommodation to adults with autistic spectrum disorder, who require 24-hour support. The building features three self-contained apartments, for those who can live more independently, as well as en-suite bedrooms, communal areas, and gardens, all specifically designed for people with autism and mental health […]

Read More

Hounslow Town Primary

Jerram Falkus Construction recently completed one of one of our most prestigious projects, The £20m project has provided a new five form entry primary school just off the High Street in Hounslow. This reinforced concrete framed, brick clad school building will be part two and part three storey, and is located on land adjacent to […]

Read More

Eleanor Smith School

Eleanor Smith School is a special educational needs school based across two sites in the London Borough of Newham. This new build site provides the School with a brand-new facility constructed on a brownfield site in East Ham.   The new Eleanor Smith School site caters for children and young people with social, emotional and […]

Read More

Macmillan Cancer Support Centre

The project comprises a complex part two/part three storey structure built in to the slope of Bristol Gate at the Royal Sussex County Hospital. The retaining walls and lower ground floor slab are constructed in reinforced cast- insitu waterproof concrete, with a partial reinforced concrete frame and upper floors and a hybrid superstructure frame of […]

Read More

The Foundry, Building B

The works to this Grade II Listed former canal-side wharf building were designed by their owner and occupant, Cullinan Studio. Achieving BREEAM ‘Excellent’ rating, the Foundry is naturally cross-ventilated while an air source heat pump serves under-floor heating. A new independent steel frame on isolated pad foundations was constructed within the existing building to support […]

Read More

Hintze Hall, Natural History Museum

One of our most prestigious projects, the Natural History Museum’s ‘Hintze Hall’ project included the refurbishment and restoration of the Grade I listed central space, creating additional gallery spaces at ground, first and second floor levels. The works comprised replacement of roof lights and conservation of the building’s listed fabric which acts as the gateway […]

Read More

Cannock Mill Cohousing

The construction of 23 new build homes, a mixture of one and two bed flats and 17 houses with up to three bedrooms with garages and useful storage space in the under croft of the six flats. The development includes the refurbishment of an Grade II listed Mill which will become a shared space for […]

Read More

East End Thames View

The redevelopment of the eastern end of the Thames View Estate in Barking provides 276 high quality affordable homes. The development was achieved without grant-funding or cross-subsidy and made possible via a private investment model designed to enable social regeneration.   The works involved the construction of five apartment blocks running north to south along […]

Read More

Wesley House

Wesley House is a post-graduate theological college, housed in 1920s Grade II listed neo-Tudor buildings. The construction works included; new Academic and Gatehouse block, new three storey accommodation block with 15 en-suite rooms, remodelling of existing 1920’s Grade II listed buildings to provide 13 en-suite student rooms with access to shared kitchen facilities, staff accommodation […]

Read More

Seven Islands Leisure Centre

The revitalisation of this leisure centre has undergone a £1 million refurbishment and has now been officially opened. Pick Everard provided mechanical and electrical building services design to assist the local authority in reducing running costs and bringing back to life a dated building. The refurbishment provides a new reception area and changing village, as […]

Read More