Jerram Falkus recently started on site at our Golders Green Road scheme.
The project consists of the construction of a six-storey block of 22 flats including basement car park.
Enabling Works: This element of the works incorporated the construction of a crossover on Golders Green Road, the removal of live services, felling of trees and shrubbery and the demolition of the existing two storey property.
Main works: Construction of six storey concrete frame and basement including 20 one-bedroom to four-bedroom flats.
Access to the main works is via Golders Green Road facilitated by a lane closure for unloading via a tower crane. The entirety of the site is fully hoarded.
The piling is complete and the capping beams have commenced. The project is anticipated to complete in Summer 2025.Golders Green Road